Build the Plan.Hold the Line.

The Schedules module turns a static Gantt into a living plan. Critical path computes itself, the field works from real lookaheads, and every slip shows up the day it happens — not at handover.

JB
Master Gantt · Apr – Oct 2026
APRMAYJUNJULAUGSEPOCT
Complete Planned Critical path

A schedule built like an operating system. Purpose-built for general contractors, ErectOS runs the master schedule as live infrastructure computing the critical path, briefing the field, and reporting the truth every single day.

Built on the critical path

A real CPM engine underneath. Forward and backward pass on every change, float tracked task by task.

Powered by Pulse

ErectOS watches every slip, delivery, and approval — and flags what it means before it costs the finish date.

Made for the field

Lookaheads your supers actually run. Progress flows back from the daily log, not the Friday meeting.

Build the plan that knows what moves the date.

Sequence the job with real dependencies, milestones, and crew loads. The moment anything changes, the longest chain to substantial completion recalculates — and every downstream date moves with it.

1.0 Plan

Master ScheduleCedar Heights
Critical Float
MAYJUNJULAUGSEPOCTNOVDEC
01Structure
Foundations
Steel Erection
Deck Pours L1–L4
02Envelope
Curtain Wall
Roofing & Waterproofing
03Interiors
MEP Rough-In
Drywall & Framing
Finishes & Commissioning
ErectOS Pulse2 min ago

Duct delivery slipped 3 days — MEP Rough-In float is gone. It now drives the finish date.

Suggested resequence

Pull Drywall — north wing forward 4 days. Recovers the Oct 5 finish.

Apply to planDismiss
1.1
Linked dependenciesFS, SS, FF, and SF with lag — move one task and everything downstream recalculates.
1.2
Milestones & gatesContract milestones, inspection holds, and owner gates tracked on the live plan.
1.3
Resource levelingCrew load per week — flatten the spikes before they become overtime.
1.4
Weather daysNon-working days and weather impacts logged straight onto the schedule with an audit trail.

The plan the field actually runs.

Roll the master down into a 3-week lookahead your supers and trades work from. Every commitment carries its constraints, so blockers get cleared before the crew shows up — not after.

2.0 Field

3-Week LookaheadWk 24 – 26
PPC last wk82%
Week 24Jun 8 – 12
Level 3 deck pourConcrete · 12ReadyPump booked, mix confirmed
Curtain wall — north faceGlazing · 8ReadyUnits staged on L2
Stair 2 steel installSteel · 6ReadyCrane window Tue–Wed
Week 25Jun 15 – 19
MEP rough-in — L2Mechanical · 14ReadyRebar delivery confirmed Thu
Roofing membraneRoofing · 5ConstraintWeather hold — 40% rain Wed
Elevator rail setVertical · 4ConstraintAwaiting inspection sign-off
Week 26Jun 22 – 26
Drywall — L1 corridorsInteriors · 10BlockedBlocked by MEP inspection
Site logistics resetGC · 3ReadyLaydown plan approved
Façade sealant passGlazing · 4ConstraintAccess — swing stage cert due
Field thread#cedar-heights
RM
RaySuper · 6:42 AM

Rebar trucks confirmed for Thu 6am — staging at gate 3.

DK
DanaPM · 6:51 AM

Good. That clears L2 rough-in for week 25.

@Pulseclear the rebar constraint
2.1
3-week lookaheadsOne click from the master schedule to the board the trades run.
2.2
Constraint trackingMaterial, RFI, and access constraints per commitment — cleared and stamped.
2.3
Percent plan completeMeasure how reliable the plan is, week over week.
2.4
Crew calendarsAssignments pushed to the calendars your team already lives in.

See the slip the day it happens.

Set a baseline at contract and track every variance against it. Planned vs earned progress at a glance, with a forecast completion date that moves with real field data — not optimism.

3.0 Track

Schedule PulseJun 11
Cedar HeightsAt risk
Pulse · 2 hrs ago
  • MEP rough-in float is gone — duct delivery slipped 3 days
  • Forecast finish moved Oct 5 → Oct 14 unless resequenced
Dockside LoftsOn track
Pulse · 5 hrs ago
  • Envelope closed in ahead of baseline by 4 days
  • Interior trades start Monday as planned
Baseline vs Actual▼ 9 days behind baseline
MAYJUNJULAUGSEPOCTNOVDEC
Planned to date55%
Earned to date46%
Forecast finishOct 14
Variance alertJun 11

Cedar Heights is 9 days behind baseline.

Planned to date55%
Earned to date46%
Forecast finishOct 14

Baseline revision BL-3 drafted — awaiting owner approval.

3.1
Locked baselinesBaseline at contract, revise with approval — full history retained.
3.2
Planned vs earnedThe S-curve that shows drift while it is still cheap to fix.
3.3
Forecast finishA completion date computed from field data, not optimism.
3.4
Change-order impactEvery CO models its schedule delta — priced and approved, not absorbed.

Wired to the whole build

Schedules reads from and writes to every module it touches — the plan and the project never drift apart.

Daily LogsField → Schedule

Field progress posts straight to % complete. The Gantt updates the night the work happens.

Change OrdersCO → Schedule

Approved COs push their schedule deltas automatically — the slip is priced before it is absorbed.

WorkforceCrews → Schedule

Crew assignments drive resource load on the plan, so leveling reflects who is actually on site.

ForecastingSchedule → Cost

Schedule slip feeds cost forecasts and completion dates the moment it appears.

The schedule updates itself. The field just builds.

Daily Logs → Schedules

Every change order prices its delay before you sign it.

Change Orders → Schedules

The finish date is computed, not negotiated.

Schedules → Forecasting

The plan is the job.Run it in ErectOS.