Forecast the finish,in dollars and days.

Cost-to-complete and final-cost forecasts that move with the schedule and the field — not with optimism.

JB
Forecasting · Cedar Heights
Forecasting · trailing 8 periods

A forecast made from optimism is a surprise waiting to happen. ErectOS computes cost-at-completion and the finish date from real production, committed cost, and approved changes so the number you carry is the number the job is actually heading toward.

Computed, not hoped

Estimate-at-completion is built from committed cost and field production — not a percentage someone typed.

Dollars and days together

Cost forecast and schedule forecast share the same data, so a slip shows up in both at once.

Powered by Pulse

Pulse surfaces the trend lines bending the wrong way while there is still room to react.

Project the cost from the real job.

Pull committed cost, actuals, and field production into a cost-to-complete that updates itself — and an estimate-at-completion you can defend to the owner.

1.0 Project

JB
Forecast · cost at completion
Forecasting · trailing 8 periods
Variance alert

EAC is trending $182k over the budget.

Budget$24.0M
EAC$24.18M
VAC-$182k
1.1
Cost to completeRemaining cost computed from real production.
1.2
Estimate at completionThe final-cost number, always current.
1.3
Productivity indexAre crews beating or trailing the plan?
1.4
Scenario compareModel recovery options side by side.

See the finish date the field is earning.

The schedule forecast moves with daily-log progress, so the completion date reflects the pace on site — not the date on the contract.

2.0 Finish

JB
Forecast · finish date
Forecasting · trailing 8 periods
ErectOS Pulse

Pulse forecasts completion on Oct 14 — 9 days late.

Driven by MEP production and CO-014 impact.

See drivers
2.1
Field-driven finishThe completion date moves with real progress.
2.2
Cash flow linkA slip reshapes the cash curve automatically.
2.3
Trend alertsPulse flags the curves bending the wrong way.
2.4
Board reportingForecast packages ready for the owner.

Wired to the whole build

Forecasting reads from and writes to every module it touches — your data is entered once and trusted everywhere.

BudgetsBudget → Forecast

Committed and actual cost feed the estimate-at-completion live.

SchedulesSchedule → Forecast

Real progress drives the forecast finish date.

Change OrdersCOs → Forecast

Approved changes adjust both cost and schedule forecasts.

Cash FlowForecast → Cash Flow

The cost and date forecast reshape the cash curve.

The finish date is computed, not negotiated.

Schedules → Forecasting

The overrun is a forecast, not a year-end surprise.

Budget → Forecasting

Dollars and days move together, off the same data.

Field → Forecasting

The forecast is the truth, early.Run it in ErectOS.